Neom set to initiate the tendering process for the construction work on The Line

 

Neom set to initiate the tendering process for the construction work on The Line

Neom is set to initiate the tendering process for the construction work on The Line, targeting the development of rafts and basements across five modules that encompass the concealed marina. The release of tender documents is expected to take place before the close of this year.

The prolific gigaproject developer has disclosed the anticipated schedule for upcoming construction contracts pertaining to various building modules and the Hidden Marina. Neom, since its launch in 2017, has been among the world's most active construction endeavors, having secured over $32 billion in contract awards.

 

Saudi Crown Prince emphasizes feasibility of THE LINE in NEOM

 

The forthcoming tenders will encompass the construction of rafts and basements for modules 44, 45, 46, 47, and 48, along with the establishment of an onsite basement precast yard facility. Neom intends to divide the work into 12 packages, including six for rafts, five for basements, and one for the basement precast yard facility.

The contract for the development of the basement precast yard facility will follow a design, build, operate, and maintain (DBOM) framework.

 

NEOM: The Line goes under construction

 

Noteworthy in the raft construction is the undertaking of the world's second-largest concrete pour, involving 43,000 cubic meters on what is referred to as the mega core.

Neom envisions companies forming joint ventures or consortiums to execute the specified construction work. A diverse array of local and international contractors attended the briefing, including Abdul Ali Al-Ajmi Company, Acciona, China Civil Engineering Construction Corporation, Larsen & Toubro, Samsung C&T, and WeBuild, among others.

Concerning the tendering timelines, the tentative request for proposals (RFP) issue date for the basement precast yard facility is slated for January, with the contract expected to be awarded by August. Subsequently, RFPs for module 46 basement erection and module 45 basement erection are scheduled for February and January 2025, respectively, with contract award dates in July 2023 and July 2025.

 

Saudi Arabia has all required resources to turn NEOM’s “The Line” into reality

 

Raft tenders are also outlined, with the RFP issue date for lots one and two set for December 24, and the bid commercial submission deadline on April 15. Contract award for these lots is expected in May. Additionally, RFPs for lots four and five are anticipated in the third quarter of 2024, with the tentative contract award date in August, while RFPs for lots six and seven are expected in the fourth quarter of 2024, with contract award anticipated by December.

This initiative aligns with Neom's shift in focus to The Line modules at the marina, where excavation work for the waterway is progressing, and the marina is poised to accommodate the world's largest cruise ships. The Line comprises 135 modules, each 800 meters in length and 500 meters tall at sea level, with the marina on the other side, presenting a significant engineering challenge to create a 165-meter-wide waterway through the towering buildings. Neom is collaborating with delivery partners, including UK-based AtkinsRealis and U.S. firms Jacobs and Parsons, for The Line.

Source: https://www.meed.com/